2017: A Year in Review

Thank you Peter Pereira for your great photos! See the SouthCoastTODAY article .Copyright 2017, Peter Pereira/The Standard-Times. All rights reserved. Used with Permission.

March 2017: The crew works to construct the laminated keelson. The double sawn timber frames are fastened with wooden trunnels and silicon bronze bolts.

photo credit: Fred Sterner

By October there has been much progress on the hull. Here workers are fairing frames for the next course of internal planks, “stringers”, which strengthen and stabilize the hull. Copyright 2017, Peter Pereira/The Standard-Times

The view from under existing foredeck looking aft showing the double sawn Danish and live oak frames and the newly installed horizontal “stringers”. Copyright 2017, Peter Pereira/The Standard-Times

Looking aft you see the great progress made since March. Keelson, clamps and stringers are complete and once the deck framing is in place the work on the deck will start. Copyright 2017, Peter Pereira/The Standard-Times

  |